| Choose the Right Wall Before Climbing |
What Comes Before Project Initiation?
Thomas
K. Sheppard · The Skillful PM™
Revised
from the September 2019 paper prepared for Open PMLC
A project can finish on time, stay within budget, and
deliver everything in its charter, yet leave the business problem untouched. By
the time the project manager receives the assignment, someone may already have
defined the problem, selected a solution, and committed to a course of action.
A team can execute those decisions with great efficiency and still spend its
time climbing a ladder that is leaning against the wrong wall.
Project managers have good reasons to concentrate on scope,
schedule, and budget. These are commitments they can manage and report on. The
difficulty comes when the organization treats delivery against those
commitments as sufficient evidence of success. That assumes the work done
before initiation established that the project could produce a worthwhile
result. If the problem was poorly understood or the wrong response was
selected, the project manager inherits a business risk that a carefully managed
schedule cannot resolve.
I call the work that should precede formal project
initiation Project Identification.
It covers the decisions that turn a perceived need for change into a defensible
proposal. It is where an organization tests strategic fit, diagnoses the
problem, weighs benefits and risks, considers alternatives, and determines
whether it can deliver the proposed change. The amount of work should be
proportionate to the decision. A change a line manager can make during normal
operations calls for a different level of analysis than an initiative that ties
up scarce specialists and funding for two years.
Project Identification has three stages. Change Identification establishes the
need and the outcome. Solution
Identification examines the causes and develops credible responses. Project Selection decides whether and
how to commit resources. Findings can send the team back to an earlier stage.
For example, an initial feasibility review might reveal that the proposed
outcome depends on an operation the sponsor has no authority to change.

Figure 1 The Three Stages of Project Identification
1. Change Identification
The first task is to decide what needs to change. A request
usually arrives in someone else’s words, and often in the form of a solution.
“We need a new system” tells you what someone wants to buy or build. It leaves
open what is failing today, who is affected, and what would count as an
improvement. Those questions apply whether the proposal originated in the
strategic plan or in a conversation with a manager.
Five sources of change
Strategic planning.
An assessment of strengths, weaknesses, opportunities, and threats can uncover
several potential changes. A proposal should make the connection to strategy
explicit. If the organization intends to take advantage of an existing
strength, what will the project enable it to do? If the proposal is meant to
reduce a threat, what exposure should change? Two proposals can cite the same
strategic priority and have very different prospects of advancing it.
Regulatory
requirements and findings. A new requirement or an examination finding can
establish an obligation and a deadline. Determine which part of the response is
prescribed and where management still has choices. A requirement may set a
standard the organization must meet while leaving it free to choose the
procedure, technology, or staffing arrangement. The cause of the exposure
remains worth investigating, especially if the organization has already tried
to fix it.
Market developments.
A strategic plan may already include contingency responses to market changes.
Other developments, such as a competitor introducing a product the organization
did not anticipate, call for a fresh assessment. Determine which customers or
operations are affected and how quickly the consequences are likely to unfold.
The urgency of the change should inform how much time the organization can
spend evaluating its response.
Audit findings.
An internal or external audit can uncover a recurring weakness, a failure to
follow an existing process, or a gap in how the organization demonstrates
compliance. Establish what must be corrected, what evidence will demonstrate
correction, and when it is due. Some findings allow management discretion about
timing. Others carry a deadline that must be reflected in the selection
decision.
Management judgment.
A manager may recognize an opportunity or notice a problem before it appears in
any formal report. The value of that observation is preserved when the manager
explains the reasoning behind it. What has changed? What evidence would support
or weaken the case? If a team hears only “because the boss said so,” it may be
able to deliver the requested output and still have no way to tell whether the
work solved the problem.
Several sources can point to the same need. An audit finding
may reveal an issue that operations staff have raised before and that a
strategic initiative is already meant to address. Compare the proposals before
committing to separate efforts. A single response may address the common cause,
or the proposals may turn out to concern different problems that merely sound
similar.
Describe the problem and the result
A useful problem statement describes the present condition,
who is affected, and why the gap matters. An opportunity statement describes
the result the organization could achieve and the circumstances that make it
attainable. In either case, establish what is already known, what needs to be
verified, and what outcome would justify doing the work.
Consider a hypothetical
audit finding. Some former employees’ system accounts remain active beyond
the required cutoff. A sponsor proposes buying a new access-management system.
Before evaluating that purchase, determine which accounts remained active, by
how long, and what evidence the audit requires. The outcome is timely removal
of access and a verifiable record of when it happened. With that outcome
stated, the organization can judge a change to its existing process on the same
terms as a proposal to buy a system.
The stage should end with enough agreement about the need
and the desired result to justify investigating a response. It may also end
with a determination that the work belongs in routine operations. That is a
useful decision in its own right, particularly when the original request came
packaged as a new project.
2. Solution Identification
Investigate causes before choosing a remedy
Organizations often react to the most visible symptom. A
corrective action can relieve the immediate pain while leaving the conditions
that produced it intact. The next time those conditions recur, the same problem
comes back. Root-cause analysis asks what has to change to prevent that
recurrence and whether the organization can make that change.
The Five Whys is a way to keep questioning the first
plausible answer. The value is in following the evidence from one answer to the
next. A single line of questioning may reveal more than one contributing cause.
Examine records, talk with the people who do the work, and test whether the
proposed explanation accounts for what happened. In an opportunity-driven
project, apply the same discipline to the conditions that would make the
opportunity achievable.
In the audit example, HR and IT could trace a sample of
departures from the time the departure was recorded through the time access was
removed. Did IT receive the notice late? Did a timely notice sit in a queue?
Did someone close the ticket while an account remained active? These
explanations point to different responses. A new system could automate the
transfer of a notice and still leave an unresolved question about who checks
that all relevant accounts were closed.
Once the causes are clearer, consider which ones the
organization can control, which it can influence, and which it must work
around. If an external party controls a step, the organization may be able to
change its own verification or escalation procedures while negotiating an
improvement with that party. The proposal should say what the response will
address and what exposure will remain.
Develop and compare responses
Suppose the audit records show that IT sometimes receives
the notification after the cutoff. One response would assign responsibility for
notifying IT and use the existing ticketing system to track and verify account
closure. Another would connect HR and IT systems so that a departure record
automatically opens a ticket. A third possibility is to introduce the process
change first and consider integration after observing how well the revised
process performs. Each option should be evaluated against the same outcome and
deadline.
Describe the benefits of each response and what has to
happen for those benefits to materialize. In the audit example, faster ticket
creation has value if the responsible team can act on the ticket and verify
account closure. The forecast should make that dependency visible. Identify the
risks of implementation and the risks that would remain after implementation.
For an optional improvement, include the consequences of continuing current
operations. For a mandatory change, compare the consequences of delay and the
merits of the feasible responses.
Treat estimates as judgments with assumptions. A single
benefit figure can conceal substantial variation in adoption, timing, or
effort. If an option looks attractive only under one favorable assumption,
investigate that assumption before committing the organization. A small test, a
review of actual records, or a conversation with the people responsible for the
operating process may be more valuable at this point than another round of
precision in a cost estimate.
Profile the proposed project using the Diamond Approach
Shenhar and Dvir’s (2007) Diamond Approach characterizes
projects along four dimensions: novelty, technology, complexity, and pace
(NTCP). I use the profile during Solution Identification to ask what each
proposed response would demand of the organization. Similar proposals can
require different kinds of oversight. The profile gives managers a way to
discuss those differences before they commit to a delivery approach.
Novelty concerns
how new the result will be to its users or market. A derivative improvement to
something familiar gives the team an existing reference point. A new platform
or a breakthrough result leaves more questions about how users will respond and
what they will consider valuable. In an internal project, I also find it useful
to ask whether a practice is new to this organization or genuinely new in the
wider world. That is a practical adaptation for discussion. It can help the
team distinguish between changes it can learn from elsewhere and changes that
will require more original testing.

Figure
2 The Diamond Approach Illustrated
Note. Each point
of the shaded profile marks the project’s category on one axis. Read the four
categories individually. Source: Shenhar and Dvir (2007).
Technology
concerns the maturity and familiarity of what the team has to use. The range in
the Diamond Approach runs from low-tech to super-high-tech. An effort using
established tools may be straightforward for an experienced team. A project
that combines familiar tools with unfamiliar technology may need a prototype or
specialized support. Where success depends on technology that still has to be
developed, the proposal should make that dependency clear and explain when the
team expects evidence that the technology can do the job.
Complexity
concerns the scope of the system and the interfaces it must handle. A change
within one operation presents a different coordination problem from a change
spanning multiple systems, departments, or organizations. For the audit
example, the integration’s difficulty would depend partly on who owns the data,
how the systems handle exceptions, and who can approve changes. A schedule that
shows when each team builds its piece should also show when the teams will test
those pieces together.
Pace concerns
what happens if the work takes longer. Regular projects allow some discretion
over timing. Fast or competitive projects face a cost for delay, such as
missing a market opportunity. Time-critical projects have a deadline whose loss
can undermine the project’s purpose. Blitz projects call for an immediate
response to a crisis. An audit date may make the corrective action
time-critical. A separate optional enhancement can have a different pace, even
when it addresses the same business problem.
Use the four dimensions as a profile. An option with
familiar technology can still be time-critical. A novel option can have
considerable flexibility over delivery dates. A single overall score can hide
the characteristic that matters most to the decision. Revisit the profile when
an assumption changes or when testing resolves a question that initially made
the project difficult to plan.
Match management involvement to the project
One reason to do this assessment before initiation is to
agree on how management will support the project. A project management office
can set common expectations for accountability, reporting, and authorization
while allowing the intensity of oversight to vary. The project manager and
sponsor should agree in advance on which decisions the team can make, which
decisions need escalation, and how promptly someone with authority will
respond.
For a familiar project with a stable plan, management by
exception may be entirely appropriate. A weekly review may provide enough
visibility, with earlier escalation when a material issue falls outside agreed
limits. An uncertain project may require more frequent decisions while the team
works through questions about requirements, technology, or interfaces. An
urgent effort may need a sponsor available daily or more often. Match the
cadence to the decisions coming up and the consequences of delay.
Table
1 How Project Pace Shapes Management
Involvement
|
Pace |
Consequence
of delay |
Management
response |
Sponsor
involvement |
|
Regular |
Timing is
flexible within agreed limits. |
Use
normal staffing and controls. Escalate material deviations. |
Review at
agreed intervals and manage by exception. |
|
Fast or competitive |
Delay can
erode a market advantage or reduce the expected benefit. |
Protect
priority work and coordinate dependencies early. |
Review
schedule risks at key milestones and clear blockers promptly. |
|
Time-critical |
Missing a
fixed deadline can undermine the purpose of the project. |
Reserve
critical staff time, monitor deadline-sensitive work, and prepare
contingencies. |
Agree on
a rapid escalation path at the outset and stay available for decisions that
could affect the deadline. |
|
Blitz |
Delay can compound the harm from
an active crisis. |
Mobilize immediately, delegate
authority, and record critical decisions and actions. |
Provide immediate access to
decision-makers and resources. |
Note. Adapted from Shenhar and Dvir (2007).
Each dimension can call for a different management response.
Novelty may warrant early feedback from users before the team fixes the design.
Technical uncertainty may warrant a proof of concept and a decision point tied
to its results. Complexity may call for named owners of interfaces and early
testing across teams. Time pressure may call for reserved specialist capacity
and a faster route to approvals. Agreeing on these responses early makes the
proposed management approach part of the feasibility decision.
Change control still matters when the plan is evolving.
Record why a change was made, what new evidence prompted it, and what it means
for the business case. A change prompted by a planned experiment is different
in origin from a change prompted by a missed commitment. Management needs to
know which situation it is dealing with. As uncertainties are resolved, the
team can make firmer commitments and use schedule and cost measures against a
more stable baseline.
For the audit example, a limited test of the existing
process may require only a few scheduled check-ins. An integration effort close
to the audit deadline could require protected access to HR and IT specialists
and a sponsor who can settle cross-department issues promptly. If that
availability cannot be secured, account for it in the selection decision. A
management approach that depends on unavailable people is a feasibility
problem.
3. Project Selection
Project Selection turns the analysis into a decision about
committing resources. A project may address a genuine problem, offer a sound
solution, and still be the wrong choice for the organization at this time. The
people authorizing the work need to consider the expected result, the
obligation or strategy it serves, the demands it places on the business, and
what the organization gives up by putting those resources here.
Assess benefits, costs, and opportunity costs
Begin with the benefits and the conditions necessary to
realize them. A proposal should make clear who gets the benefit, when it can be
expected, and how it will be measured. It should also account for the costs of
implementing and sustaining the change. In the audit example, configuring a
ticketing system is only part of the cost. Someone must own the revised
process, review exceptions, and retain the evidence the organization needs.
The choice of financial method depends on what the decision
requires. The following methods from the original paper are useful when their
assumptions and limitations are visible (Monnappa, 2018).
Table
2 Methods for Comparing Project
Proposals
|
Method |
What
it tells you |
Main
limitation |
|
Benefit-cost ratio |
Present
value of benefits per dollar of present-value cost. |
Can favor
a smaller project that creates less total value. |
|
Payback period |
How long
it takes to recover the initial investment. |
Simple
payback omits later cash flows and the time value of money. |
|
Return on investment |
Net
benefit relative to investment cost. |
Depends
on consistent cost definitions and time horizons. |
|
DCF and net present value |
Net value
today of expected project cash flows. |
Sensitive
to cash-flow forecasts and the discount rate. |
|
Internal rate of return |
The
discount rate at which net present value is zero. |
Can rank
projects differently from NPV when size or timing differs. |
|
Economic value added |
Incremental
operating profit after tax and a charge for capital. |
Depends
on estimating both operating profit and capital employed. |
|
Opportunity cost |
What the
organization gives up by using its capacity here. |
The value
of the best forgone alternative can be hard to quantify. |
|
Weighted
scoring |
How proposals compare across
agreed criteria. |
Rankings depend on the evidence,
scores, and weights used. |
Note. Methods
summarized from the discussion that follows. See Monnappa (2018) for the
original overview.
Benefit-cost ratio.
Divide the present value of expected benefits by the present value of expected
costs, using a consistent treatment of the timing and categories of both. A
ratio above one means the benefits included in the calculation exceed the costs
included in it. The ratio can help compare value per unit of cost, while the
absolute value created may matter when deciding between projects of different
sizes.
Payback period.
Payback estimates how long it will take to recover the initial investment from
net cash inflows. With level annual net inflows, divide the initial investment
by the annual amount. When the inflows vary, track them cumulatively to find
the recovery point. Simple payback gives an indication of how long capital is
committed before recovery. It leaves out cash flows after that point and uses
undiscounted amounts.
Return on investment
(ROI). A simple project ROI expresses net benefit as a share of investment
cost. State what is included as a benefit and cost, what period the calculation
covers, and whether the amounts are discounted. An apparent advantage can
disappear when the comparison uses common definitions and time horizons.
Discounted cash flow
and net present value (NPV). Discounting expresses future cash flows in
present-value terms using a stated rate. NPV adds the present values of all
expected net cash flows, including the initial investment. A positive NPV
indicates that the forecast cash flows exceed the return implied by the chosen
discount rate. The estimate depends on the quality of the cash-flow forecasts
and the rate selected. A mandatory project may have a negative financial NPV
and still require action. Comparing the present cost of remedies that satisfy
the same obligation may be a better use of the analysis.
Internal rate of
return (IRR). IRR is a discount rate at which NPV equals zero. A percentage
return can be convenient to communicate. When alternatives differ in size or
the timing of cash flows, IRR and NPV can rank them differently. Review the
actual cash flows and the value the project is expected to create before using
the higher percentage as a basis for selection.
Economic value added
(EVA). EVA measures operating profit after tax less a charge for the
capital employed. Its usefulness in project selection depends on the ability to
estimate the incremental operating profit and capital required. State both
assumptions if using it to compare proposals.
Opportunity cost.
The relevant cost of using scarce capacity includes the value of the best
feasible alternative forgone. That may be another project, a service
improvement the operating team will have to delay, or work that could otherwise
be done by the same specialists. Include that consequence in the decision even
when it is difficult to express in dollars.
A weighted scoring model can make judgments visible when
financial measures capture only part of the decision. Agree on the criteria and
weights before scoring proposals. Explain what each score means and record the
evidence behind it. Test whether plausible changes in weights or estimates
change the ranking. Where a requirement is mandatory, treat it as a condition
of eligibility. A high score elsewhere cannot compensate for a remedy that
misses a binding deadline.
Test feasibility against real constraints
Feasibility is a question about this organization, with its
existing commitments, at the time the work would need to be done. The NTCP
profile helps identify what to test. A solution that depends on new technology
may call for a technical trial. One that crosses organizational boundaries may
hinge on access to people or decisions. A time-critical project may depend on a
test environment being available on a particular date. Identify the constraints
that could overturn the selection decision and check them before authorization.
Personnel.
Subject matter experts are often the people the business depends on to keep
daily operations running. Listing an expert in a resource plan is easy.
Securing that person’s time at the point the project needs it is harder. Ask
the line manager what the person is already committed to, who can cover
recurring work, and whether the project can move activities to a less congested
period. Include the staff who will test the change, train users, and support it
after delivery. They may be different from the people building it.
Facilities and
infrastructure. Check the working arrangements, facilities, and systems the
project will need. A project that can operate across locations may still
require shared test environments, access to production-like data, or time in a
facility for a trial. Establish when those resources will be available and who
controls them. A project schedule based on resources that another team has
already reserved needs to be revised.
Funding. Approval
of a proposal can reduce funding available for other projects or operating
activities. Establish what is funded, what remains contingent, and who can make
a decision if costs change. Consider the funding needed to operate or maintain
the result after the project closes. An organization that pays to implement a
change but gives the operating team no capacity to sustain it has left part of
the business case unanswered.
Schedule and capacity
for change. Check the timing of business cycles, operating peaks, other
project releases, and any external deadlines. An organization may have
sufficient people in total and still be unable to absorb several changes at
once. Where dates can move, compare the consequences of resequencing against
the cost and practicality of adding capacity. Where dates are fixed,
distinguish the work needed to achieve the result by that date from
enhancements that can be considered later.
In the audit example, a process trial might show that the
existing ticketing system can record responsibility, require verification, and
produce suitable evidence. The integration option might also satisfy the
requirement, but depend on a specialist unavailable until after the deadline.
That is a reason to authorize the process change and defer integration. If the
trial instead shows that the process cannot generate adequate evidence, revise
the proposal and seek a remedy that can meet the requirement.
Make and record the decision
Strategic alignment belongs throughout Project
Identification. At selection, state the connection in terms of the result. An
initiative may advance a specific business objective, protect an essential
operation, or meet a binding obligation. An optional proposal that cannot show
what it will contribute is a candidate for deferral or rejection. A mandatory
obligation still calls for a deliberate choice about how to satisfy it.
Say explicitly whether the proposal will proceed to
initiation, go back for revision or further evidence, be deferred, or be
declined. Record who made the decision and the reasoning behind it. Include
conditions that could trigger reconsideration, such as evidence that the
technology cannot meet a requirement or that a promised resource is
unavailable. When corrective work is mandatory, declining a particular proposal
leaves the obligation open and someone must remain responsible for finding an
acceptable response.
Carry the business case into initiation
Use project strategy to connect the decision to delivery
Strategic Project Leadership expands the discussion of
project success to encompass the results the organization sought when it
approved the project. Shenhar et al. (2001) describe project success in
multiple dimensions, and Shenhar et al. (2007) position project strategy as the
link between business strategy and project planning. That link matters because
a team will encounter choices that were never made in the selection meeting. It
needs a basis for deciding which trade-offs the sponsor would accept and which
would put the purpose of the work at risk.

Figure
3 Project Strategy as the Link Between
Business Strategy and Delivery
Note. Source:
Shenhar et al. (2007).
Project strategy should explain how the project will create
or protect value and how that purpose will guide the work. For a product
project it might define how the result will compete in the market. For the
audit project it would define how the organization intends to correct the
control failure and demonstrate that the correction is working. In each case,
the strategy should be specific enough to inform decisions about scope,
sequencing, and acceptable risk.
Link to business
strategy. Carry forward the objective or obligation that justified the
project, the result expected, and the reasoning for selecting this response. In
the audit example, the sponsor should make clear that the purpose is to remove
access by the required cutoff and be able to show that it happened. That makes
the reporting and verification steps integral to the work.
Vision and team
purpose. Give the people doing the work a clear picture of the operating
condition they are trying to create. A description of what should happen on the
next employee departure gives HR, IT, and the operating owner a shared goal. It
also gives them a basis for recognizing a gap while they can still change the
design.
Organization.
Assign roles and decision authority that support both delivery and the business
outcome. Identify the sponsor, who can resolve resource conflicts, and the
person who will own the result in operations. A project manager can coordinate
the handoff and help establish the measures. The person accountable for the
process after delivery needs the authority and resources to act on those
measures.
Processes. Choose
planning, review, testing, and change-control practices that fit the project’s
characteristics. Use what the NTCP assessment revealed about uncertainty and
pace. A team may need early trials where feasibility is unclear and tighter
schedule control where a deadline is fixed. Agree on who can approve changes
that affect the business outcome.
Tools. Select
tools that support the practices the team needs. A schedule can help coordinate
delivery. An operating record can show whether a control is working. In the
audit example, the ability to verify and retrieve evidence of closure should
influence tool selection from the outset.
Protect continuity through the handoffs
In my experience as a management consultant and project
manager, handoffs are opportunities to lose the reasoning behind a project. The
people who framed the need may turn the work over to a delivery team. That team
may then turn the implemented change over to the people who will run it. At
each transfer, it is possible to convey the tasks and deliverables while losing
the assumptions and decisions that explain them.
Bring the project manager and the eventual operating owner
into the discussion early enough to question the proposal and understand how
the sponsor expects it to produce the desired result. Carry the business case
into initiation with the alternatives considered, the assumptions that
mattered, the expected measures, and the names of the people responsible for
the relevant decisions. During delivery, use that record when a proposed change
could affect the outcome. At handoff to operations, confirm where the data will
come from, who will review it, and when the first review will take place.
For the audit example, completion of the revised workflow is
a delivery milestone. The operating owner can then review the proportion of
applicable accounts closed by the required cutoff and whether those closures
have supporting evidence. An exception should prompt a review of what occurred
and whether the control or its execution needs attention. That is how the
organization learns whether the response it selected is producing the result it
expected.
Conclusion
Efficiency deserves attention. A well-run project makes
disciplined use of the people, money, and time entrusted to it. The work of
Project Identification gives that discipline a sound purpose. It helps an
organization decide which changes warrant a project, which responses are worth
pursuing, and which commitments it can reasonably make.
Before you begin planning your next project, ask the sponsor
three questions. What business result are we trying to achieve? Why do we
believe this project will achieve it? What will we measure after delivery to
find out whether it did? Where those answers are unclear, return to the
selection work with the people who can resolve them.
References
Monnappa, A.
(2018, October 4). Project selection
methods for project management professionals. Simplilearn.
https://www.simplilearn.com/project-selection-methods-article
Shenhar, A. J.,
& Dvir, D. (2007). Reinventing
project management: The diamond approach to successful growth and innovation.
Harvard Business Review Press.
Shenhar, A. J.,
Dvir, D., Levy, O., & Maltz, A. C. (2001). Project success: A
multidimensional strategic concept. Long
Range Planning, 34, 699–725.
Shenhar, A.,
Milosevic, D., Dvir, D., & Thamhain, H. (2007). Linking project management to business strategy. Project Management
Institute.