Monday, November 16, 2026

Before Project Initiation

Choose the Right Wall Before Climbing

What Comes Before Project Initiation?

Thomas K. Sheppard · The Skillful PM™

Revised from the September 2019 paper prepared for Open PMLC

A project can finish on time, stay within budget, and deliver everything in its charter, yet leave the business problem untouched. By the time the project manager receives the assignment, someone may already have defined the problem, selected a solution, and committed to a course of action. A team can execute those decisions with great efficiency and still spend its time climbing a ladder that is leaning against the wrong wall.

Project managers have good reasons to concentrate on scope, schedule, and budget. These are commitments they can manage and report on. The difficulty comes when the organization treats delivery against those commitments as sufficient evidence of success. That assumes the work done before initiation established that the project could produce a worthwhile result. If the problem was poorly understood or the wrong response was selected, the project manager inherits a business risk that a carefully managed schedule cannot resolve.

I call the work that should precede formal project initiation Project Identification. It covers the decisions that turn a perceived need for change into a defensible proposal. It is where an organization tests strategic fit, diagnoses the problem, weighs benefits and risks, considers alternatives, and determines whether it can deliver the proposed change. The amount of work should be proportionate to the decision. A change a line manager can make during normal operations calls for a different level of analysis than an initiative that ties up scarce specialists and funding for two years.

Project Identification has three stages. Change Identification establishes the need and the outcome. Solution Identification examines the causes and develops credible responses. Project Selection decides whether and how to commit resources. Findings can send the team back to an earlier stage. For example, an initial feasibility review might reveal that the proposed outcome depends on an operation the sponsor has no authority to change.

Figure 1  The Three Stages of Project Identification

1. Change Identification

The first task is to decide what needs to change. A request usually arrives in someone else’s words, and often in the form of a solution. “We need a new system” tells you what someone wants to buy or build. It leaves open what is failing today, who is affected, and what would count as an improvement. Those questions apply whether the proposal originated in the strategic plan or in a conversation with a manager.

Five sources of change

Strategic planning. An assessment of strengths, weaknesses, opportunities, and threats can uncover several potential changes. A proposal should make the connection to strategy explicit. If the organization intends to take advantage of an existing strength, what will the project enable it to do? If the proposal is meant to reduce a threat, what exposure should change? Two proposals can cite the same strategic priority and have very different prospects of advancing it.

Regulatory requirements and findings. A new requirement or an examination finding can establish an obligation and a deadline. Determine which part of the response is prescribed and where management still has choices. A requirement may set a standard the organization must meet while leaving it free to choose the procedure, technology, or staffing arrangement. The cause of the exposure remains worth investigating, especially if the organization has already tried to fix it.

Market developments. A strategic plan may already include contingency responses to market changes. Other developments, such as a competitor introducing a product the organization did not anticipate, call for a fresh assessment. Determine which customers or operations are affected and how quickly the consequences are likely to unfold. The urgency of the change should inform how much time the organization can spend evaluating its response.

Audit findings. An internal or external audit can uncover a recurring weakness, a failure to follow an existing process, or a gap in how the organization demonstrates compliance. Establish what must be corrected, what evidence will demonstrate correction, and when it is due. Some findings allow management discretion about timing. Others carry a deadline that must be reflected in the selection decision.

Management judgment. A manager may recognize an opportunity or notice a problem before it appears in any formal report. The value of that observation is preserved when the manager explains the reasoning behind it. What has changed? What evidence would support or weaken the case? If a team hears only “because the boss said so,” it may be able to deliver the requested output and still have no way to tell whether the work solved the problem.

Several sources can point to the same need. An audit finding may reveal an issue that operations staff have raised before and that a strategic initiative is already meant to address. Compare the proposals before committing to separate efforts. A single response may address the common cause, or the proposals may turn out to concern different problems that merely sound similar.

Describe the problem and the result

A useful problem statement describes the present condition, who is affected, and why the gap matters. An opportunity statement describes the result the organization could achieve and the circumstances that make it attainable. In either case, establish what is already known, what needs to be verified, and what outcome would justify doing the work.

Consider a hypothetical audit finding. Some former employees’ system accounts remain active beyond the required cutoff. A sponsor proposes buying a new access-management system. Before evaluating that purchase, determine which accounts remained active, by how long, and what evidence the audit requires. The outcome is timely removal of access and a verifiable record of when it happened. With that outcome stated, the organization can judge a change to its existing process on the same terms as a proposal to buy a system.

The stage should end with enough agreement about the need and the desired result to justify investigating a response. It may also end with a determination that the work belongs in routine operations. That is a useful decision in its own right, particularly when the original request came packaged as a new project.

2. Solution Identification

Investigate causes before choosing a remedy

Organizations often react to the most visible symptom. A corrective action can relieve the immediate pain while leaving the conditions that produced it intact. The next time those conditions recur, the same problem comes back. Root-cause analysis asks what has to change to prevent that recurrence and whether the organization can make that change.

The Five Whys is a way to keep questioning the first plausible answer. The value is in following the evidence from one answer to the next. A single line of questioning may reveal more than one contributing cause. Examine records, talk with the people who do the work, and test whether the proposed explanation accounts for what happened. In an opportunity-driven project, apply the same discipline to the conditions that would make the opportunity achievable.

In the audit example, HR and IT could trace a sample of departures from the time the departure was recorded through the time access was removed. Did IT receive the notice late? Did a timely notice sit in a queue? Did someone close the ticket while an account remained active? These explanations point to different responses. A new system could automate the transfer of a notice and still leave an unresolved question about who checks that all relevant accounts were closed.

Once the causes are clearer, consider which ones the organization can control, which it can influence, and which it must work around. If an external party controls a step, the organization may be able to change its own verification or escalation procedures while negotiating an improvement with that party. The proposal should say what the response will address and what exposure will remain.

Develop and compare responses

Suppose the audit records show that IT sometimes receives the notification after the cutoff. One response would assign responsibility for notifying IT and use the existing ticketing system to track and verify account closure. Another would connect HR and IT systems so that a departure record automatically opens a ticket. A third possibility is to introduce the process change first and consider integration after observing how well the revised process performs. Each option should be evaluated against the same outcome and deadline.

Describe the benefits of each response and what has to happen for those benefits to materialize. In the audit example, faster ticket creation has value if the responsible team can act on the ticket and verify account closure. The forecast should make that dependency visible. Identify the risks of implementation and the risks that would remain after implementation. For an optional improvement, include the consequences of continuing current operations. For a mandatory change, compare the consequences of delay and the merits of the feasible responses.

Treat estimates as judgments with assumptions. A single benefit figure can conceal substantial variation in adoption, timing, or effort. If an option looks attractive only under one favorable assumption, investigate that assumption before committing the organization. A small test, a review of actual records, or a conversation with the people responsible for the operating process may be more valuable at this point than another round of precision in a cost estimate.

Profile the proposed project using the Diamond Approach

Shenhar and Dvir’s (2007) Diamond Approach characterizes projects along four dimensions: novelty, technology, complexity, and pace (NTCP). I use the profile during Solution Identification to ask what each proposed response would demand of the organization. Similar proposals can require different kinds of oversight. The profile gives managers a way to discuss those differences before they commit to a delivery approach.

Novelty concerns how new the result will be to its users or market. A derivative improvement to something familiar gives the team an existing reference point. A new platform or a breakthrough result leaves more questions about how users will respond and what they will consider valuable. In an internal project, I also find it useful to ask whether a practice is new to this organization or genuinely new in the wider world. That is a practical adaptation for discussion. It can help the team distinguish between changes it can learn from elsewhere and changes that will require more original testing.

Figure 2  The Diamond Approach Illustrated

Note. Each point of the shaded profile marks the project’s category on one axis. Read the four categories individually. Source: Shenhar and Dvir (2007).

Technology concerns the maturity and familiarity of what the team has to use. The range in the Diamond Approach runs from low-tech to super-high-tech. An effort using established tools may be straightforward for an experienced team. A project that combines familiar tools with unfamiliar technology may need a prototype or specialized support. Where success depends on technology that still has to be developed, the proposal should make that dependency clear and explain when the team expects evidence that the technology can do the job.

Complexity concerns the scope of the system and the interfaces it must handle. A change within one operation presents a different coordination problem from a change spanning multiple systems, departments, or organizations. For the audit example, the integration’s difficulty would depend partly on who owns the data, how the systems handle exceptions, and who can approve changes. A schedule that shows when each team builds its piece should also show when the teams will test those pieces together.

Pace concerns what happens if the work takes longer. Regular projects allow some discretion over timing. Fast or competitive projects face a cost for delay, such as missing a market opportunity. Time-critical projects have a deadline whose loss can undermine the project’s purpose. Blitz projects call for an immediate response to a crisis. An audit date may make the corrective action time-critical. A separate optional enhancement can have a different pace, even when it addresses the same business problem.

Use the four dimensions as a profile. An option with familiar technology can still be time-critical. A novel option can have considerable flexibility over delivery dates. A single overall score can hide the characteristic that matters most to the decision. Revisit the profile when an assumption changes or when testing resolves a question that initially made the project difficult to plan.

Match management involvement to the project

One reason to do this assessment before initiation is to agree on how management will support the project. A project management office can set common expectations for accountability, reporting, and authorization while allowing the intensity of oversight to vary. The project manager and sponsor should agree in advance on which decisions the team can make, which decisions need escalation, and how promptly someone with authority will respond.

For a familiar project with a stable plan, management by exception may be entirely appropriate. A weekly review may provide enough visibility, with earlier escalation when a material issue falls outside agreed limits. An uncertain project may require more frequent decisions while the team works through questions about requirements, technology, or interfaces. An urgent effort may need a sponsor available daily or more often. Match the cadence to the decisions coming up and the consequences of delay.

Table 1  How Project Pace Shapes Management Involvement

Pace

Consequence of delay

Management response

Sponsor involvement

Regular

Timing is flexible within agreed limits.

Use normal staffing and controls. Escalate material deviations.

Review at agreed intervals and manage by exception.

Fast or competitive

Delay can erode a market advantage or reduce the expected benefit.

Protect priority work and coordinate dependencies early.

Review schedule risks at key milestones and clear blockers promptly.

Time-critical

Missing a fixed deadline can undermine the purpose of the project.

Reserve critical staff time, monitor deadline-sensitive work, and prepare contingencies.

Agree on a rapid escalation path at the outset and stay available for decisions that could affect the deadline.

Blitz

Delay can compound the harm from an active crisis.

Mobilize immediately, delegate authority, and record critical decisions and actions.

Provide immediate access to decision-makers and resources.

Note. Adapted from Shenhar and Dvir (2007).

Each dimension can call for a different management response. Novelty may warrant early feedback from users before the team fixes the design. Technical uncertainty may warrant a proof of concept and a decision point tied to its results. Complexity may call for named owners of interfaces and early testing across teams. Time pressure may call for reserved specialist capacity and a faster route to approvals. Agreeing on these responses early makes the proposed management approach part of the feasibility decision.

Change control still matters when the plan is evolving. Record why a change was made, what new evidence prompted it, and what it means for the business case. A change prompted by a planned experiment is different in origin from a change prompted by a missed commitment. Management needs to know which situation it is dealing with. As uncertainties are resolved, the team can make firmer commitments and use schedule and cost measures against a more stable baseline.

For the audit example, a limited test of the existing process may require only a few scheduled check-ins. An integration effort close to the audit deadline could require protected access to HR and IT specialists and a sponsor who can settle cross-department issues promptly. If that availability cannot be secured, account for it in the selection decision. A management approach that depends on unavailable people is a feasibility problem.

3. Project Selection

Project Selection turns the analysis into a decision about committing resources. A project may address a genuine problem, offer a sound solution, and still be the wrong choice for the organization at this time. The people authorizing the work need to consider the expected result, the obligation or strategy it serves, the demands it places on the business, and what the organization gives up by putting those resources here.

Assess benefits, costs, and opportunity costs

Begin with the benefits and the conditions necessary to realize them. A proposal should make clear who gets the benefit, when it can be expected, and how it will be measured. It should also account for the costs of implementing and sustaining the change. In the audit example, configuring a ticketing system is only part of the cost. Someone must own the revised process, review exceptions, and retain the evidence the organization needs.

The choice of financial method depends on what the decision requires. The following methods from the original paper are useful when their assumptions and limitations are visible (Monnappa, 2018).

Table 2  Methods for Comparing Project Proposals

Method

What it tells you

Main limitation

Benefit-cost ratio

Present value of benefits per dollar of present-value cost.

Can favor a smaller project that creates less total value.

Payback period

How long it takes to recover the initial investment.

Simple payback omits later cash flows and the time value of money.

Return on investment

Net benefit relative to investment cost.

Depends on consistent cost definitions and time horizons.

DCF and net present value

Net value today of expected project cash flows.

Sensitive to cash-flow forecasts and the discount rate.

Internal rate of return

The discount rate at which net present value is zero.

Can rank projects differently from NPV when size or timing differs.

Economic value added

Incremental operating profit after tax and a charge for capital.

Depends on estimating both operating profit and capital employed.

Opportunity cost

What the organization gives up by using its capacity here.

The value of the best forgone alternative can be hard to quantify.

Weighted scoring

How proposals compare across agreed criteria.

Rankings depend on the evidence, scores, and weights used.

Note. Methods summarized from the discussion that follows. See Monnappa (2018) for the original overview.

Benefit-cost ratio. Divide the present value of expected benefits by the present value of expected costs, using a consistent treatment of the timing and categories of both. A ratio above one means the benefits included in the calculation exceed the costs included in it. The ratio can help compare value per unit of cost, while the absolute value created may matter when deciding between projects of different sizes.

Payback period. Payback estimates how long it will take to recover the initial investment from net cash inflows. With level annual net inflows, divide the initial investment by the annual amount. When the inflows vary, track them cumulatively to find the recovery point. Simple payback gives an indication of how long capital is committed before recovery. It leaves out cash flows after that point and uses undiscounted amounts.

Return on investment (ROI). A simple project ROI expresses net benefit as a share of investment cost. State what is included as a benefit and cost, what period the calculation covers, and whether the amounts are discounted. An apparent advantage can disappear when the comparison uses common definitions and time horizons.

Discounted cash flow and net present value (NPV). Discounting expresses future cash flows in present-value terms using a stated rate. NPV adds the present values of all expected net cash flows, including the initial investment. A positive NPV indicates that the forecast cash flows exceed the return implied by the chosen discount rate. The estimate depends on the quality of the cash-flow forecasts and the rate selected. A mandatory project may have a negative financial NPV and still require action. Comparing the present cost of remedies that satisfy the same obligation may be a better use of the analysis.

Internal rate of return (IRR). IRR is a discount rate at which NPV equals zero. A percentage return can be convenient to communicate. When alternatives differ in size or the timing of cash flows, IRR and NPV can rank them differently. Review the actual cash flows and the value the project is expected to create before using the higher percentage as a basis for selection.

Economic value added (EVA). EVA measures operating profit after tax less a charge for the capital employed. Its usefulness in project selection depends on the ability to estimate the incremental operating profit and capital required. State both assumptions if using it to compare proposals.

Opportunity cost. The relevant cost of using scarce capacity includes the value of the best feasible alternative forgone. That may be another project, a service improvement the operating team will have to delay, or work that could otherwise be done by the same specialists. Include that consequence in the decision even when it is difficult to express in dollars.

A weighted scoring model can make judgments visible when financial measures capture only part of the decision. Agree on the criteria and weights before scoring proposals. Explain what each score means and record the evidence behind it. Test whether plausible changes in weights or estimates change the ranking. Where a requirement is mandatory, treat it as a condition of eligibility. A high score elsewhere cannot compensate for a remedy that misses a binding deadline.

Test feasibility against real constraints

Feasibility is a question about this organization, with its existing commitments, at the time the work would need to be done. The NTCP profile helps identify what to test. A solution that depends on new technology may call for a technical trial. One that crosses organizational boundaries may hinge on access to people or decisions. A time-critical project may depend on a test environment being available on a particular date. Identify the constraints that could overturn the selection decision and check them before authorization.

Personnel. Subject matter experts are often the people the business depends on to keep daily operations running. Listing an expert in a resource plan is easy. Securing that person’s time at the point the project needs it is harder. Ask the line manager what the person is already committed to, who can cover recurring work, and whether the project can move activities to a less congested period. Include the staff who will test the change, train users, and support it after delivery. They may be different from the people building it.

Facilities and infrastructure. Check the working arrangements, facilities, and systems the project will need. A project that can operate across locations may still require shared test environments, access to production-like data, or time in a facility for a trial. Establish when those resources will be available and who controls them. A project schedule based on resources that another team has already reserved needs to be revised.

Funding. Approval of a proposal can reduce funding available for other projects or operating activities. Establish what is funded, what remains contingent, and who can make a decision if costs change. Consider the funding needed to operate or maintain the result after the project closes. An organization that pays to implement a change but gives the operating team no capacity to sustain it has left part of the business case unanswered.

Schedule and capacity for change. Check the timing of business cycles, operating peaks, other project releases, and any external deadlines. An organization may have sufficient people in total and still be unable to absorb several changes at once. Where dates can move, compare the consequences of resequencing against the cost and practicality of adding capacity. Where dates are fixed, distinguish the work needed to achieve the result by that date from enhancements that can be considered later.

In the audit example, a process trial might show that the existing ticketing system can record responsibility, require verification, and produce suitable evidence. The integration option might also satisfy the requirement, but depend on a specialist unavailable until after the deadline. That is a reason to authorize the process change and defer integration. If the trial instead shows that the process cannot generate adequate evidence, revise the proposal and seek a remedy that can meet the requirement.

Make and record the decision

Strategic alignment belongs throughout Project Identification. At selection, state the connection in terms of the result. An initiative may advance a specific business objective, protect an essential operation, or meet a binding obligation. An optional proposal that cannot show what it will contribute is a candidate for deferral or rejection. A mandatory obligation still calls for a deliberate choice about how to satisfy it.

Say explicitly whether the proposal will proceed to initiation, go back for revision or further evidence, be deferred, or be declined. Record who made the decision and the reasoning behind it. Include conditions that could trigger reconsideration, such as evidence that the technology cannot meet a requirement or that a promised resource is unavailable. When corrective work is mandatory, declining a particular proposal leaves the obligation open and someone must remain responsible for finding an acceptable response.

Carry the business case into initiation

Use project strategy to connect the decision to delivery

Strategic Project Leadership expands the discussion of project success to encompass the results the organization sought when it approved the project. Shenhar et al. (2001) describe project success in multiple dimensions, and Shenhar et al. (2007) position project strategy as the link between business strategy and project planning. That link matters because a team will encounter choices that were never made in the selection meeting. It needs a basis for deciding which trade-offs the sponsor would accept and which would put the purpose of the work at risk.

Figure 3  Project Strategy as the Link Between Business Strategy and Delivery

Note. Source: Shenhar et al. (2007).

Project strategy should explain how the project will create or protect value and how that purpose will guide the work. For a product project it might define how the result will compete in the market. For the audit project it would define how the organization intends to correct the control failure and demonstrate that the correction is working. In each case, the strategy should be specific enough to inform decisions about scope, sequencing, and acceptable risk.

Link to business strategy. Carry forward the objective or obligation that justified the project, the result expected, and the reasoning for selecting this response. In the audit example, the sponsor should make clear that the purpose is to remove access by the required cutoff and be able to show that it happened. That makes the reporting and verification steps integral to the work.

Vision and team purpose. Give the people doing the work a clear picture of the operating condition they are trying to create. A description of what should happen on the next employee departure gives HR, IT, and the operating owner a shared goal. It also gives them a basis for recognizing a gap while they can still change the design.

Organization. Assign roles and decision authority that support both delivery and the business outcome. Identify the sponsor, who can resolve resource conflicts, and the person who will own the result in operations. A project manager can coordinate the handoff and help establish the measures. The person accountable for the process after delivery needs the authority and resources to act on those measures.

Processes. Choose planning, review, testing, and change-control practices that fit the project’s characteristics. Use what the NTCP assessment revealed about uncertainty and pace. A team may need early trials where feasibility is unclear and tighter schedule control where a deadline is fixed. Agree on who can approve changes that affect the business outcome.

Tools. Select tools that support the practices the team needs. A schedule can help coordinate delivery. An operating record can show whether a control is working. In the audit example, the ability to verify and retrieve evidence of closure should influence tool selection from the outset.

Protect continuity through the handoffs

In my experience as a management consultant and project manager, handoffs are opportunities to lose the reasoning behind a project. The people who framed the need may turn the work over to a delivery team. That team may then turn the implemented change over to the people who will run it. At each transfer, it is possible to convey the tasks and deliverables while losing the assumptions and decisions that explain them.

Bring the project manager and the eventual operating owner into the discussion early enough to question the proposal and understand how the sponsor expects it to produce the desired result. Carry the business case into initiation with the alternatives considered, the assumptions that mattered, the expected measures, and the names of the people responsible for the relevant decisions. During delivery, use that record when a proposed change could affect the outcome. At handoff to operations, confirm where the data will come from, who will review it, and when the first review will take place.

For the audit example, completion of the revised workflow is a delivery milestone. The operating owner can then review the proportion of applicable accounts closed by the required cutoff and whether those closures have supporting evidence. An exception should prompt a review of what occurred and whether the control or its execution needs attention. That is how the organization learns whether the response it selected is producing the result it expected.

Conclusion

Efficiency deserves attention. A well-run project makes disciplined use of the people, money, and time entrusted to it. The work of Project Identification gives that discipline a sound purpose. It helps an organization decide which changes warrant a project, which responses are worth pursuing, and which commitments it can reasonably make.

Before you begin planning your next project, ask the sponsor three questions. What business result are we trying to achieve? Why do we believe this project will achieve it? What will we measure after delivery to find out whether it did? Where those answers are unclear, return to the selection work with the people who can resolve them.

References

Monnappa, A. (2018, October 4). Project selection methods for project management professionals. Simplilearn. https://www.simplilearn.com/project-selection-methods-article

Shenhar, A. J., & Dvir, D. (2007). Reinventing project management: The diamond approach to successful growth and innovation. Harvard Business Review Press.

Shenhar, A. J., Dvir, D., Levy, O., & Maltz, A. C. (2001). Project success: A multidimensional strategic concept. Long Range Planning, 34, 699–725.

Shenhar, A., Milosevic, D., Dvir, D., & Thamhain, H. (2007). Linking project management to business strategy. Project Management Institute.

About the Author

Tom Sheppard is an experienced program and project manager specializing in managing large ($10mm+), high-risk, high-profile projects in the US Financial Services market. Author of "The Art of Project Management." More than 20 years experience in project management in banking and financial services with a PMP and MPM. More than 25 years experience in systems design, development, and management with a BSCS/MIS. Former US Marine and a former missionary. Fluent in English and Spanish. Experienced instructor. Successful business owner, international author and public speaker. His LinkedIn Profile is: http://linkedin.com/in/tsheppard Specialties: Program management, project management, change management, process design, business case development, negotiation, multi-tier system architecture, real-time parallel distributed databases, private placements and creative finance.

(c) Copyright 2026  The Skillful PM, LLC. All Rights Reserved. 

Your comments are welcome. Please observe some ground rules. No profanity, vulgarity, or personal attacks. Facts are always welcome.

Before Project Initiation

Choose the Right Wall Before Climbing What Comes Before Project Initiation? Thomas K. Sheppard · The Skillful PM™ Revised from the September...